Before accepting an order, establish three things: exactly what the customer wants, whether your proposed offer matches it and whether you can deliver that offer under the stated conditions. An attractive price and a familiar product code do not resolve a conflicting drawing or create missing capacity.
This is an operational review for sales and delivery teams. It is not legal advice, a complete contract checklist or a claim that these fields alone satisfy an ISO standard. Commercial, statutory, safety or sector-specific requirements may need additional competent review.
Make the intended commitment visible
ISO’s public explanation of quality assurance describes a process-focused approach to meeting requirements consistently. ASQ’s supplier-quality guidance likewise highlights specifications, technical capability, capacity and delivery reliability. S1S2 The record below applies those general ideas to the seller’s decision before committing to a customer.
Gather the customer request, your quotation, referenced specifications and proposed delivery terms in one review. Identify revisions rather than relying on the latest email in someone’s inbox. Write down how successful delivery will be recognised: the product or service, quantity, required evidence, destination and date or milestone.
For each difference, record who must resolve it and what confirmation will count. Do not silently choose the convenient version. A customer may accept a different date or specification, but the changed offer must become an explicit agreed basis before the team treats the conflict as closed.
A fictional order that is not ready to accept
All figures and records here are fictional. A customer requests 100 assembled kits. The purchase order refers to drawing revision A, an attachment contains revision B and the quotation was costed on A. The requested delivery is 27 October at 15:00. These dates are part of the invented example, not a real customer commitment.
| Review item | Evidence in the fictional file | Disposition |
|---|---|---|
| Product revision | Order says A; attached drawing says B | Hold: ask which revision is required and reassess the affected work. |
| Quantity and acceptance | 100 kits; agreed functional test report required | Plan must include production and final checks. |
| Delivery request | 27 October, 15:00; destination confirmed | Capacity review required before promising it. |
| Price basis | Quotation calculated using revision A | Recheck if B is confirmed; no silent substitution. |
Even if revision A is confirmed, the draft production plan does not fit. The current estimate is six qualified work minutes per kit, plus 30 minutes of setup and 60 minutes for final checking. Required work is 100 × 6 + 30 + 60 = 690 minutes. The planner has documented 660 net qualified minutes available before the requested completion point, after existing commitments and planned unavailability. The shortfall is 30 minutes, or half an hour.
Do not treat that small gap as rounding noise. Nor does finding another 30 minutes prove the promise is feasible. Materials, sequencing, equipment, competent personnel and transport must also fit. Six work minutes per kit is a planning input, not a measured guarantee; revision B could change the estimate.
One conditional option fits the stated work-minute limit: if the customer agrees to 90 kits of revision A, assembly takes 90 × 6 = 540 minutes. Keeping the same 30-minute setup and 60-minute final-check allowance gives 630 minutes, leaving 30 of the available 660 minutes. This is feasible only against that capacity constraint. It still needs explicit agreement on quantity, price and acceptance, plus confirmation of materials, sequencing and transport before the delivery promise can be approved. The fixed setup and checking allowances are fictional planning assumptions, not generally valid scaling rules.
Write a decision that prevents accidental acceptance
| Order review OR-026-v1 | Completed fictional entry |
|---|---|
| Current disposition | Hold operational acceptance. No confirmed delivery promise may be issued from this record. |
| Reason | Unresolved drawing revision and a 30-minute shortfall under the revision-A plan. |
| Owner | Sales manager coordinates customer clarification; operations planner owns feasibility evidence. |
| Proposed options | A 90-kit revision-A option requires 630 of 660 available minutes, leaving 30 minutes. It is not accepted until the customer agrees and all other feasibility checks close. A later delivery or authorised capacity adjustment would need its own revised plan. |
| Evidence needed to close | Customer confirmation of the intended revision and agreed offer; approved capacity and materials plan; resolved price and acceptance evidence. |
| Release condition | Named authorised person records the selected feasible option and the supporting document revisions. |
The decision is a hold, not a refusal. It tells the team what evidence would allow a responsible commitment. Keep tentative options clearly marked so a provisional planning email is not mistaken for a customer agreement. Use the organisation’s actual authority rules for who can confirm an offer.
Reopen the affected checks when the order changes
A later quantity increase, drawing revision or earlier delivery request can invalidate an earlier review. Identify which assumptions changed, reassess the affected work and preserve the previous decision. Do not replace a historical commitment with the new date in the performance record merely because the revised plan is easier to meet.
The review should remain proportionate. A repeat order with unchanged requirements may reuse current evidence, provided capacity and other time-sensitive assumptions are checked. A new product or unusual acceptance condition may need technical input before anyone can estimate the work credibly.
For the next uncertain order, write one sentence beginning “We are committing to…” and attach the exact specification, date and acceptance basis. Resolve every material difference, calculate the available capacity and record who authorised the final commitment.
Prepared with AI-assisted research and drafting. Reviewed by: QSE Advisory experts.
Sources
This article is general information. Verify current requirements and seek qualified advice for your specific circumstances.