For an order-level OTIF measure, count an order as successful only when its complete agreed requirement arrives within the agreed time condition. Join its partial deliveries back to that order before calculating the rate. A high proportion of units arriving on time is a different measure and can coexist with a low OTIF result.

APQC describes on-time-in-full delivery in terms of orders delivered complete and within the agreed time frame. S1 Detailed reporting rules still need to be explicit. The due-date cohort and receipt rules below are QSE’s proposed internal method, not a universal contractual interpretation or a claim that every benchmark uses the same formula.

Fix the promise and denominator first

The fictional distributor reports orders whose agreed receipt deadline falls within one reporting week. Each order remains in that week’s denominator whether delivered, partly delivered or still undelivered at cutoff. The example has five eligible orders, no cancellations or authorised promise changes, one product line per order, and a common unit that can validly be summed.

An order passes if all agreed units are received by its deadline and are of the agreed item and condition. Earlier partial receipts are permitted in this example. Keep the original promise and any properly authorised revision as separate fields. Quietly moving the deadline after a miss changes the story rather than improving delivery.

Reassemble the order from its receipts

Order / required unitsWhat arrivedOrder OTIF
A / 100All 100 by deadlinePass
B / 10090 by deadline; 10 lateFail
C / 50All 50 lateFail
D / 200100 then 100; both by deadlinePass
E / 40Nothing by deadlineFail

All quantities and events are fictional. The order result is 2 successful orders ÷ 5 eligible orders × 100 = 40% OTIF. D passes despite being split because its complete requirement meets the stated rule. B fails despite most of its quantity arriving on time. E remains a failed due order, not an invisible missing receipt.

Removing E because it has no receipt record would report 2 ÷ 4 = 50%. That is an incomplete order population. Start from the due-order register, attach receipts to it and check unmatched records; starting only from receipts can omit the work that never arrived.

Explain why the quantity result differs

The required quantity is 100 + 100 + 50 + 200 + 40 = 490 units. Units received on time total 100 + 90 + 0 + 200 + 0 = 390. Therefore 390 ÷ 490 × 100 = 79.6% of required units arrived on time, rounded to one decimal place. This is a quantity-weighted on-time measure, not the 40% order-level OTIF result.

Neither denominator should be swapped into the other label. An order measure gives each order one outcome; a quantity measure gives more weight to larger quantities. Do not sum incompatible units, such as boxes and individual items, without a justified conversion. If the customer commitment is defined by order line instead, build and label a line-level measure before aggregating; a passing line does not automatically make the whole order successful.

Keep four boundary cases in the definition

  • Wrong item or unusable receipt: do not treat the number of packages at the dock as proof that the agreed requirement is complete. Keep acceptance evidence and the delivery timing evidence distinguishable.
  • Approved changes: retain who agreed what and when. State which promise version the report uses; show the effect of a legitimate revision rather than overwriting history.
  • Cancellations and returns: define the treatment before running the report. The example has none; it cannot decide a real contractual exception for you.
  • Zero eligible orders: report the rate as not applicable with a zero denominator, not 100% or 0% success.

Make the next action specific

Completed fictional report noteEntry
Population evidenceFive orders due in the week; five matched report rows
OutcomeTwo pass, three fail; OTIF 40%
Diagnostic quantity measure390 of 490 units on time; 79.6%
First follow-upOrder owner investigates B’s late balance, C’s late order and E’s missing delivery separately
LimitFive orders illustrate the method; no trend or supplier benchmark inferred

Retain order ID, agreed line quantities, deadline and timezone, receipt IDs, accepted quantities, exceptions and outcome. Test one split order, one late balance and one undelivered due order before trusting an automated report. Your next practical step is to reproduce five real orders from these fields and resolve disagreements in the definition before publishing a percentage.

Source and editorial disclosure

QSE Advisory is published by QSE Advisory (office@qseadvisory.com). Research, drafting and the recorded editorial checking pass were AI assisted. Every worked scenario is fictional.

Prepared with AI-assisted research and drafting. Reviewed by: QSE Advisory experts.

Sources

  1. S1 · Percentage of orders delivered complete and on time (on time in full)

This article is general information. Verify current requirements and seek qualified advice for your specific circumstances.

Reviewed by QSE Advisory experts

Every article is researched, sourced and checked before publishing.

Editorial standards →