Start with a piece of work that actually got stuck. Map who received it, what they needed, when they acted and why it waited. A tidy sequence of department names will not explain a delay if it hides the conditions for accepting the next step.
This method is for a process owner investigating routine cross-team work such as an order amendment. It produces a current-state map and a proposed handoff agreement. It does not establish a contractual service level or prove the cause of delay from timestamps alone.
Fix the boundaries before drawing boxes
ASQ’s flowchart guidance recommends defining the start and end, putting actual steps in sequence and checking the map with people who do the work. It treats inputs, outputs, decisions and timing as useful process detail. S1 For a delayed amendment, a useful start is when the customer’s request arrives; a useful finish is when a confirmed response is sent.
Keep the first-arrival timestamp even if the request is incomplete. Add a separate “ready for processing” timestamp if you need one. Resetting the start to the moment a complete packet appears would hide the customer’s earlier wait. Choose calendar or working time explicitly; do not switch between them during the calculation.
Reconcile one fictional journey
All entries below are fictional. One routine amendment arrives at 09:00 and receives a confirmed response at 15:00 on the same working day. The example contains no breaks, overnight periods, parallel activities or hidden work. Its elapsed time is six hours, or 360 minutes.
| Interval | Activity or wait | Minutes |
|---|---|---|
| 09:00–09:10 | Sales checks request | 10 |
| 09:10–11:00 | Waiting for Planning | 110 |
| 11:00–11:15 | Planning reviews change | 15 |
| 11:15–13:00 | Waiting for Finance | 105 |
| 13:00–13:20 | Finance checks price | 20 |
| 13:20–14:50 | Waiting for Sales response | 90 |
| 14:50–15:00 | Sales confirms to customer | 10 |
Touch time totals 55 minutes: 10 + 15 + 20 + 10. Waiting totals 305 minutes: 110 + 105 + 90. Together they reconcile to 360 minutes. Waiting is 84.7% of this case’s elapsed time, rounded to one decimal place. That is a description of one case, not an average for the process or a promised saving.
The longest wait is worth examining, but duration does not identify its cause. A queue, an absent decision-maker, missing information or an unresolved priority conflict could produce the same timestamp pattern. Ask what the receiving team was waiting for and preserve the supporting record.
Map the acceptance condition at each transfer
In the fictional walkthrough, Planning says it needs an approved price basis before committing the revised production date. Sales had assumed Finance would review price only after Planning supplied the date. The map has exposed an incompatible assumption. Simply asking both teams to work faster would not settle it.
| Transfer | Required receiving evidence | Incomplete-work route |
|---|---|---|
| Sales to Planning | Customer request, current order revision and a stated price-review status | Planning identifies the missing item and returns a reason to the named Sales owner. |
| Planning to Finance | Feasible options and their cost drivers; unresolved assumptions visible | Finance requests a specific clarification without silently treating assumptions as approved. |
| Finance to Sales | Approved price basis, conditions and the option reviewed | Sales reconciles the chosen option before making a customer commitment. |
These proposed local rules require agreement on what a provisional feasibility check authorises before price approval. If activities run in parallel, show the overlap and calculate elapsed time without counting it twice.
A completed improvement record
| Record PM-024-v1 | Fictional entry |
|---|---|
| Observed issue | Sales and Planning use different definitions of a ready amendment. |
| Proposed change | Add price-review status and one named Sales owner to each amendment packet. Allow a clearly labelled feasibility check before final price approval. |
| Accountable owner | Order-process owner; Planning and Finance agree the acceptance conditions. |
| Verification before rollout | Walk three recent cases through the current map, including an incomplete request. Accept the map only when each participating team can trace the actual transfers, receiving conditions and return paths with no unexplained step or unassigned owner. |
| Follow-up | For the next ten eligible amendments after an authorised change, record the timeline and hold reasons, together with case complexity, available staffing and queue at arrival. |
| Decision still pending | Whether the change reduces avoidable waiting without increasing rework or premature commitments. |
These are proposed checks. The map can be accepted when the walkthrough condition is met; a claim of faster performance needs separate evidence. The single 360-minute case is not a representative baseline. Compare similar cases under comparable workload and staffing, and report case-level differences rather than promising a saving from the fictional 305 waiting minutes.
Take one delayed item to the people who handled it. Reconcile the full timeline, document each receiving team’s acceptance condition and include the return path for incomplete work. Improve the first verified mismatch before turning the map into a polished diagram.
Prepared with AI-assisted research and drafting. Reviewed by: QSE Advisory experts.
Sources
This article is general information. Verify current requirements and seek qualified advice for your specific circumstances.